Jobsite description

 

This project consists of a 5 lanes, 760 meters long curved bridge over the Wouri river.
65 000 m³ of concrete are used.

CHRYSO expertise

CHRYSO®Optima 145 and CHRYSO®Tard CHR used to deliver a flowable concrete, easily pumpable with a long workability retention despite temperatures up to 40°C.

Products used

  • CHRYSO®Optima 145
  • CHRYSO®Tard CHR

Project technical challenges

Underwater casting of piles (C 40/50) at a depth of 60 meters with a workability retention of 8 hours in tropical temperatures.
Casting of the large prestressed deck segments (C50/60) with 2 hours workability retention.


Project participants

Owner: State of Cameroon
Constructor: Sogea Satom, Soletanche Bachy (VINCI Construction)

Other references

Freeway

HIGH-FIVE INTERCHANGE

Construction of a five-level freeway interchange to replace former interchange which has been modified for freeway speeds.

DALLAS, UNITED STATES
View reference
HIGH-FIVE INTERCHANGE
Real estate

THE LEONARDO ENTRANCE

The Leonardo began construction on 17 November 2015.
It is a 55 floor mixed-use property development in Sandton, Johannesburg, South Africa that stands at a height of 234 metres.

SANDTONE, SOUTH AFRICA
View reference
THE LEONARDO ENTRANCE